Enforcement Action Summary Fiscal Year 2005
Clean Water Act (CWA)
Chaffee Excavating
Courneyor, Paul d/b/a Courneyor Septic
Services
Degussa Initiators LLC (August 03, 2005)
Degussa Initiators, LLC (September 23, 2005)
Fujicolor Processing Inc.
Indiana Department of Environmental Management
Lake Erie Iron and Metal Company, Inc., et
al.
Minden Bog, Michigan
Minnesota Center for Environmental Advocacy
Northern Indiana Public Service Company (NIPSCO)
Schrum, Jeffery
Sockness Septic Service
Wood River, Illinois
Court of Federal Claims Dismisses Takings Claims Filed Against EPA and Corps Relating to Michigan Peat CWA Section 404 Permitting Matter for the Minden Bog, Michigan. On November 13, 2003, the Court of Federal Claims dismissed all five counts of a takings action brought by Bay-Houston Towing Company (Bay-Houston)against EPA and the Army Corps of Engineers (Corps) in connection with the federal Clean Water Act (CWA), section 404 enforcement and permitting activities, for Bay-Houston's 2800-acre Minden Bog property in Michigan. On approximately 950 acres of the property, Bay-Houston had mined peat for years without a CWA section 404 permit. In 1998, EPA filed an enforcement action seeking penalties and injunctive relief consisting of reclamation and restoration of those 950 acres (although the district court found Bay-Houston liable for many section 404 violations, the court decided not to assess any penalties and has stayed consideration of injunctive relief). The balance of the property is unmined. Although the State of Michigan administers the CWA section 404 permit program, because the state was unable to issue a section 404 permit that met EPA's concerns, and in 1997 actually issued a state wetlands permit allowing peat mining on most of the entire 2800-acre property, the Corps became the federal permitting authority for the Minden Bog property as of 1997. In late 1998, the Company submitted a permit application to the Corps for only the 950 historically-mined acres.
In its takings action, the Bay-Houston alleged that both the 950-acre
parcel and the balance of its property had been “taken”
under either a categorical or severe diminution taking theory, and
alleged a temporary taking. The court found that none of the claims
were ripe: a) the 950-acre parcel is still the subject of a Corps
permitting process; b) the Corps as the federal permitting authority
has never made a final permitting decision on the undisturbed acreage,
nor had the opportunity to do so (when the state wetlands permit
was issued, the state was not then acting as the federal permitting
authority); and, c) no temporary taking arose because the permit
process neither has been extraordinarily lengthy nor have the federal
agencies acted in bad faith. The court also rejected
the Bay-Houston's arguments that applying to the Corps for permission
to mine the undeveloped acres would be "futile": while
the court recognized that the federal government places a high ecological
value on the Minden Bog property and wants to minimize the extent
of peat mining, the court did not have sufficient evidence to conclude
that the Corps would refuse to allow peat mining and associated
discharges on all of the undisturbed acreage.
Contact: Jacqueline Miller, Multi-Media Branch II, (312) 886-7167.
Region 5 Approves Indiana E.
Coli TMDL for Trail Creek. In an effort to achieve
the Clean Water Act goal of “fishable, swimmable” waters,
Section 303(d)of the Clean Water Act, and U.S. EPA’s implementing
regulations at 40 C.F.R. Part 130, the EPA requires states to develop
Total Maximum Daily Loads (“TMDLs”) for pollutants in
impaired waters. On March 1, 2004, the Region approved the TMDL
submitted to U.S. EPA by Indiana Department of Environmental Management
to address E. coli levels in Trail Creek, an impaired water in Northwest
Indiana. The TMDL establishes the maximum daily load of E.
coli coming from point and non-point sources at which the Creek
still meets the applicable water quality standard. The Region’s
review ensures that the TMDL and its supporting documentation meet
statutory and regulatory requirements. (Double click TMDL's for more information)
Contact: Erik Olson, 312-886-6829;
additional contact: David Werbach, 312-886-4242
Region signs CAFO
settling Clean Water Act case. On June 16, the Acting Regional
Administrator signed a Consent Agreement and Final Order, settling
In the Matter of Paul Cournoyer, d/b/a Cournoyer Septic Services,
Docket No. CWA-05-2003-0011. The CAFO requires Mr. Cournoyer to
certify that he is in compliance with federal regulations concerning
land disposal of domestic septage and to pay a $250 fine. On April
15, 2003, EPA filed an administrative complaint against Mr. Cournoyer,
who was doing business as Cournoyer Septic Services in Pittsville,
Wisconsin. The complaint alleged that Mr. Cournoyer violated the
Clean Water Act by failing to comply with federal regulations concerning
land disposal of domestic septage. Mr. Cournoyer was subsequently
discharged in bankruptcy under Chapter 7. The penalty amount in
the CAFO reflects Mr. Cournoyer’s limited ability to pay a
penalty.
Primary contact - Timothy Thurlow, Associate Regional Counsel, 312-886-6623.
Region 5 enters a Consent Agreement and Final Order resolving an administrative CWA against Fujicolor Processing, Inc., Crawfordsville, Indiana. On November 6, 2003, Region 5 filed an administrative complaint against Fujicolor Processing, Inc. (Fuji), alleging violations of the local pretreatment standards for silver, as set forth in its industrial wastewater pretreatment permit, issued by the City of Crawfordsville, Indiana’s publicly own treatment works. The complaint sought a penalty of $85,000. Prior to Fuji’s filing an answer, the parties agreed to settle the matter by a Consent Agreement and Final Order filed with the Regional Hearing Clerk on May 28, 2004. The settlement required Fuji to certify that it is full compliance with the CWA, 33 U.S.C. § 1311 et seq., and the regulations promulgated thereunder at 40 C.F.R. Part 403, and to pay the entire civil penalty of $85,000.
Contact: Susan Tennenbaum, Associate Regional Counsel at 312-886-0273
Region 5 issues CWA 309(a) Administrative
Compliance Order to Chaffee Excavating, Vanderbilt, MI On August 20, 2004, Region 5 issued an administrative Findings of
Violation and Order for Compliance (“Compliance Order”)
under Section 309(a) of the Clean Water Act (“CWA”),
33 U.S.C. § 1319(a), to Chaffee Excavating, a septage waste
hauler located at 477 East Thumb Lake Road, Vanderbilt, Michigan,
requiring Chaffee Excavating to comply with an information request
issued by Region 5 on May 6, 2004, under Section 308 of the CWA,
33 U.S.C. § 1318, relating to Chaffee Excavating’s compliance
with the domestic septage land application requirements set forth
at 40 C.F.R. Part 503. Chaffee Excavating refused to submit the
requested information, challenging U.S. EPA’s authority to
issue information requests on numerous grounds and returning a copy
of the information request with the phrase “Refused for Cause
Without Dishonor” handwritten on each page. The parties subsequently
engaged in correspondence, but Chaffee Excavating maintained its
challenge to U.S. EPA’s jurisdiction and still refused to
provide the requested information. The Compliance Order resulted.
Section 309(a)(4) of the CWA requires U.S. EPA to provide Chaffee
Excavating with an opportunity to confer before the order becomes
effective.
Primary Contact: Kevin Chow, (312) 353-6181; Additional Contact:
Valdis Aistars, (312) 886-0264.
On November 24, 2004, U.S. EPA Issued
a Clean Water Act Section 311 (OPA) Administrative Order on Consent
for the Bowman Creek (3) Oil Spill Site, to the Northern
Indiana Public Service Company (NIPSCO), for Performance of a
Removal Action and Cost Reimbursement at the Bowman Creek (3)
Site in South Bend, Indiana (St. Joseph County). This AOC requires
NIPSCO to perform removal actions and to reimburse U.S. EPA and
the U.S. Coast Guard for oversight costs at the Bowman Creek
(3)(South Bend, St. Joseph County, Indiana) Oil Spill site. NIPSCO
is required to address and remove all oil and oily-like substances
entering Bowman Creek as a result of coal tar and other petroleum-related
discharges from the upstream NIPSCO South Bend, IN facility.
Pursuant to the Order, under the direction of a U.S. EPA on-scene
coordinator and to the extent necessary to abate an imminent
and substantial threat to the public health or welfare at Bowman
Creek, NIPSCO will address the ground and surface water, soils,
and creek contamination from the Bowman Creek (3) Oil Spill Area. NIPSCO
is currently addressing long-term source control matters at its
facility through the Indiana Department of Environmental Management
voluntary clean-up program.
Bowman Creek is a tributary of the St. Joseph River in northern Indiana and
a navigable water of the United States under the CWA. Bowman Creek passes through
South Bend, IN. In February 2000, a release of diesel oil from the area of
the Grand Trunk Western Railroad (GTWR) facility adjacent to the north bank
(and downstream from the current Site) of Bowman Creek prompted a State of
Indiana investigation and referral to US EPA. US EPA negotiated and issued
a CWA Section 311 AOC to GTWR in March 2000 (Bowman Creek Site 1). The GTWR
work was completed in 2002, except for oversight and maintenance (Bowman Creek
Site 2) which is on-going. At the conclusion of its removal work, GTWR conducted
a study and reported to U.S. EPA that an additional source of petroleum discharge
to Bowman Creek was discernible from an upstream source. Follow up investigation
by U.S. EPA determined that NIPSCO was responsible for the upstream contamination.
In Spring 2004, U.S. EPA began formal negotiations with NIPSCO in order to
address the oil discharge. An AOC was negotiated, and issued on November 24,
2004.
Primary Contact: Thomas Turner, Associate Regional Counsel, 312-886-3337.
Region 5 enters into a Consent Agreement
and Final Order with LEIMCO Development Company, Ltd. et al., Painesville,
Ohio - On June 5, 2003, Region 5 issued Findings of Violations and
a Compliance Order to Respondents Lake Erie Iron & Metal Company, Inc.,
Martin Hathy and Richard M. Osborne, Sr., who are owners/members of LEIMCO
Development Company, Ltd. The Order alleged that Respondents violated Section
301 of the CWA, 33 U.S.C. §1311, by discharging pollutants into approximately
34 acres of federal jurisdictional wetlands within LEIMCO Development-owned
property without either a CWA Section 404 or Section 402 permit (33 U.S.C. §§ 1344,
1342); and failing to provide all information requested pursuant to CWA Section
308, 33 U.S.C. § 1318. The violations and related circumstances supported
a proposed civil penalty of $137,500. Respondents subsequently provided additional
information, indicating that approximately 28.72 acres of wetlands were impacted
within the LEIMCO Development-owned property. On April 22, 2005, following
a public comment period, Region 5 entered into a Consent Agreement and Final
Order (CAFO), resolving the violation. The CAFO requires payment of a $75,000
civil penalty; compliance with the CWA; submission of a revised after-the-fact
CWA Section 404 permit application to the U.S. Corps of Engineers, Buffalo
District, including a Mitigation-Replacement Plan, detailing mitigation of
approximately 44 acres within a 340-acre Mitigation Site to be purchased by
Respondents and third-parties; restoration and enhancement with third-parties
of approximately 71 acres of the Site; and performance of a SEP, consisting
of the donation of the Site to Lake County Metroparks in perpetuity with land
use restrictions and restoration of biological and habitat functions for approximately
23 acres of the Site. The SEP will accomplish environmental restoration and
protection by enhancing hydrological and biological conditions and habitat
within the Grand River watershed. Both the LEIMCO Development-owned property
and the Mitigation Site are located within the Grand River watershed.
Contact Diana Embil, Associate Regional Counsel, primary contact, 312-886-7889,
or David Schulenberg, Wetlands Enforcement Coordinator, additional contact, 312-886-6680.
District Court in Minnesota Grants
Motion for Summary Judgment Remanding Regional Fecal TMDL to
EPA and the State. On June 23, 2005, the U.S. District
Court, District of Minnesota, granted in part and denied in part
as moot the Minnesota Center for Environmental Advocacy’s
(MCEA) summary judgment motion challenging EPA’s approval
of a regional TMDL for the Lower Mississippi River Basin for
fecal coliform bacteria. The TMDL covered seven subwatersheds
and 20 impaired segments. On September 30, 2003, MCEA filed the
lawsuit challenging EPA’s approval of the TMDL under the
APA, 5 U.S.C. § 706(2)(A). MCEA’s summary judgment
motion claimed that EPA’s approval of the TMDL was arbitrary
and capricious because it established a basin-wide target of
65% that would not achieve water quality standards in the most
impaired segments, lacked an adequate margin of safety, and improperly
included point sources (municipal storm sewers systems, CAFOs,
and illicit straight pipe discharges), in the load allocation
portion of the TMDL. MCEA’s motion asked the Court to remand
the TMDL to EPA to re-calculate the TMDL. The State subsequently
informed EPA that it intends to amend the TMDL to address many
of the problems identified by MCEA, and include 25 additional
impaired segments. In its reply to the summary judgment motion
EPA did not oppose a remand in order to allow the State to revise
the TMDL to achieve applicable water quality standards, to include
an adequate margin of safety, and to assign municipal storm sewers
and CAFOs to the wasteload allocation. While the Court agreed
with EPA that neither the Clean Water Act nor regulations prohibit
a watershed or basin-wide TMDL, it found that to the extent EPA
approved a TMDL that was not set to achieve water quality standards,
EPA was in error. Furthermore, the Court found that municipal
storm sewers, CAFOs and illicit straight pipes are all point
sources that must be included in the waste load allocation. Finally,
the Court found that the margin safety issues raised by the Plaintiff
moot since the State intends to revise the TMDL and margin of
safety. The Court ordered the State to public notice a revised
TMDL for all impaired reaches within 90 days of judgment. If
the State fails to notice a revised TMDL within the 90 days,
the Court ordered EPA to establish a replacement TMDL within
30 days thereafter.
Contacts: ORC, Craig Melodia (312) 353-8870; OGC, Jim Curtin
United States Files Complaint Against
Degussa Initiators, LLC, and Simultaneously lodges Consent Decree
in Southern District of Ohio resolving Clean Water Act violations.
On August 3, 2005, the United States filed a complaint against Degussa Initiators,
LLC and simultaneously lodged a consent decree resolving violations of the Clean
Water Act at Degussa’s facility in Elyria, Ohio. This action was lodged
with the United States District Court for the Northern District of Ohio (Civil
Action No. 1:05CV1915). The consent decree resolves numerous violations of Sections
307(d) and 308 of the Clean Water Act, 33 U.S.C. §§ 1317(d) and 1318,
including violation of categorical and local pretreatment effluent limits contained
in industrial user permits issued by the Elyria, Ohio publicly owned treatment
works. The proposed decree provides that Degussa will pay a civil penalty of
$345,203.50 and will perform a supplemental environmental project valued at $27,514.
The project is the installation of a floating roof for the facility’s pretreatment
equalization tank to mitigate emissions of volatile organic compounds to the
ambient air. Degussa also certifies in the proposed decree that it has implemented
corrective measures necessary to ensure continuous compliance with applicable
effluent limits and other permit terms, and establishes stipulated penalties
if noncompliance occurs in the future.
Primary Contact: Mark Palermo, ORC, (312) 886-6082; additional contact: Purita Angeles, (312) 353-5112
United States District Court for
the Southern District of Ohio Enters Consent Decree Resolving
CWA Violations by Licking County, Ohio
On August 31, 2005, the United States District Court for the Southern District
of Ohio entered a Consent Decree resolving CWA violations by Licking County,
Ohio. On July 5, 2005, the United States filed a complaint against Licking County
and simultaneously lodged a consent decree resolving violations of the Clean
Water Act, Civil Action No. C2-05- 661 (S.D. Ohio). No comments were received
on the consent decree during the public comment period. The consent decree resolves
numerous violations of the terms of the National Pollutant Discharge Elimination
System (NPDES) permit for the Buckeye Lake waste water treatment plant (WWTP)
and a December 12, 1994 administrative order issued by U.S. EPA. Violations include
exceeding effluent limitations, bypassing or overflowing untreated wastewater,
and violating the monitoring, testing and sludge management requirements of the
NPDES permit. In addition, Licking County violated the sludge standards at 40
C.F.R. Part 503. The consent decree requires Licking County to pay a civil penalty
of $37,500 to the United States and $37,500 to the State of Ohio. The State of
Ohio is identified as a realigned plaintiff in the consent decree.
To resolve the violations identified in the complaint, Licking County installed storage basins to provide additional storage capability and reduce bypasses while a permanent solution is developed. In addition, Licking County conducted an infiltration/inflow (I/I) study and has removed the largest sources of I/I identified in the study. Licking County has also developed a corrective action plan, and will remove additional I/I sources from the sewer system, construct capital improvements and develop a preventive maintenance program. Capital improvements will include construction of the wet stream and sludge handling facilities necessary to effectively increase the rated capacity of the WWTP so that all flows reaching the headworks will receive full treatment. Improvements may include, but are not limited to, the construction of a new biological reactor, new final clarifiers, additional sludge digestion and storage facilities and associated electrical and site improvements. The consent decree requires these improvements to be fully operational by December 1, 2007.
Primary Contact: Christine Liszewski, (312) 886-4670; additional
contact: Bettye Carter, (312) 886-6705.
Consent Judgment Entered in United
States v. Degussa Initiators, LLC, Resolving Clean Water Act
Violations at Elyria, Ohio Facililty. On September
23, 2005, the Northern District of Ohio approved a consent decree
and entered a consent judgment in a federal civil case, United
States. v. Degussa Initiators, LLC. On August 3, 2005, the United
States filed a complaint against Degussa Initiators, LLC and
simultaneously lodged a consent decree resolving violations of
the Clean Water Act at Degussa’s facility in Elyria, Ohio
(Civil Action No. 1:05CV1915). The consent decree resolves numerous
violations of Sections 307(d) and 308 of the Clean Water Act,
33 U.S.C. §§ 1317(d) and 1318, including violation
of categorical and local pretreatment effluent limits contained
in industrial user permits issued by the Elyria, Ohio publicly
owned treatment works. The proposed decree provides that Degussa
will pay a civil penalty of $345,203.50 and will perform a supplemental
environmental project valued at $27,514. The project is the installation
of a floating roof for the facility’s pretreatment equalization
tank to mitigate emissions of volatile organic compounds to the
ambient air. Degussa also certifies in the proposed decree that
it has implemented corrective measures necessary to ensure continuous
compliance with applicable effluent limits and other permit terms,
and establishes stipulated penalties if noncompliance occurs
in the future.
Contact: Mark Palermo: (312)886-6082; Purita Angeles: (312)353-5112.
Findings of Violation and Compliance
Order issued September 19, 2005, requires an Ohio property owner
to remove culverts and fill materials from waters of the United
States.
On September 19, 2005, the U.S. EPA, Region 5 issued to Jeffrey Schrum a Compliance
Order requiring Mr. Schrum to remove culverts and fill materials from Indian
Run, a tributary of the Mahoning River. Without obtaining a permit from the Corps
of Engineers, Mr. Schrum used backhoes, bulldozers and other heavy equipment
to place end-to-end within Indian Run several old storage tanks with diameters
of between eight and ten feet. The storage tanks act as a makeshift culvert and
have a length of approximately one hundred and thirty feet. He then placed fill
material on top of the storage tanks. The fill material has a depth of between
six and eight feet. The Corps twice demanded that Mr. Schrum either apply for
an after-the-fact permit or remove the tanks and fill material. Mr. Schrum ignored
these demands. U.S. EPA made a similar demand in June 2005 which Mr. Schrum again
ignored. The Order requires Mr. Schrum to submit within thirty days a plan to
remove the culverts and restore Indian Run to its original condition and contours.
Contacts: Steven P. Kaiser at (312) 353-3804 (legal contact) or David Schulenberg at (312) 886-6680 (technical contact).
Region 5 issues Administrative Order,
under Section 308 and 309 of the CWA to the City of Wood River,
Illinois, in connection with combined sewer overflows (CSOs).
On September 29, 2005, Region 5 issued to the City of Wood River, Illinois, an
administrative compliance order, pursuant to CWA section 309, based on a joint
EPA-Illinois inspection of the City’s WWTP and the fact that, in recent
years, the City has had many CSO events. Because a number of requested records
were not available during the inspection, the administrative order also seeks
information pursuant to CWA section 308. It appears that the City is not complying
with all of the federal CSO nine minimum controls, including maximizing flow
to the WWTP and maximizing storage of wastewaters in order to prevent CSO events.
The administrative order not only directs the City to demonstrate its compliance
with, and/or come into compliance with, the nine minimum controls, but also directs
the City to prepare, and to submit to EPA, a long-term control plan within one
year. This is the first such CWA administrative compliance order to be issued
by Region 5.
Primary Contact: Jacqueline Miller, ORC, (312) 886-7167 and John Wiemhoff, Water
Division, (312) 353-8546.
Region issues to Fredrick Maki of Watton,
Michigan an Administrative Complaint Seeking Civil Penalties
for Violations of the Clean Water Act.
On September 29, 2005, Region 5 issued to Fredrick Maki an Administrative Complaint
seeking civil penalties for violations of the Clean Water Act. The Complaint
alleges that on or about September 10, 2003, and on or about July 24, 2004,
Maki applied to land surfaces in the Upper Peninsula of Michigan domestic septage
but failed to either ensure that by alkali addition the pH of the septage remained
at 12 or higher for 30 minutes with the addition of more alkali, or to incorporate
the domestic septage into the soil within six hours after application to or
placement on the land in violation of Section 405(3) of the Clean Water Act.
The Complaint further alleges that Maki failed to develop and retain information
in connection with the application of domestic septage as required by 40 CFR
503.17(B) and failed to provide information responsive to U.S. EPA’s
information request in violation of Section 308(a) of the Clean Water Act.
The Region has proposed a civil penalty in the amount of one-hundred thousand
dollars ($100,000.00).
Contact: Steven Kaiser, ORC, (312) 353-3804.
Region 5 files Administrative Complaint
against Sockness Septic Service
On September 21, 2005, Region 5 filed an Administrative
Complaint under 40 CFR Part 22 against Sockness Septic Service. Sockness
operates a septage collection and hauling service near Stanley, Wisconsin.
EPA alleges that Sockness violated EPA’s septage regulations
at 40 CFR Part 503 by failing to meet vector attraction reduction
requirements and by failing to develop and maintain adequate records.
The complaint
proposes a penalty of $44,723.
Contacts: Chuck Mikalian, primary contact, (312) 886-2242; Valdis Aistars, secondary contact, (312) 886-0264.
![[logo] US EPA](http://www.epa.gov/epafiles/images/logo_epaseal.gif)