Jump to main content.


Reach D, Pollution Report 2

Tittabawassee River Dioxin-Reach D
Midland, MI - EPA Region V
POLREP #2 - 7/27/2007
On-Scene Coordinators - James Augustyn and Brian Schlieger

Site Description

On July 9, 2007, Dow's contractor began positioning equipment on a work barge to begin the preparation of driving temporary sheet piling in the river to delineate the area of highest dioxin contamination. Dow's contractor has completed construction on the HDPE sediment transport pipeline and has conducted hydrostatic testing of the line. The sediment transport line is approximately 9,000 feet long and will transport sediment slurry from the dredge area in the river to the Geo-Tube dewatering cell.

On-Scene Coordinators (OSC) Jim Augustyn and Brian Schlieger are providing oversight with assistance from U.S. EPA's START Contractor, Weston Solutions, Inc.

Current Activities

The following tasks have been completed by Dow's contractors during the period of July 23-27, 2007:

Planned Removal Actions

Installation of sheet piling above the bridge is nearly complete. The sheet piling will be driven down to established elevations to complete the installation. Turbidity monitors will be placed in the river to monitory potential increases in turbidity that may result from excavation of material from the river bank adjacent to the RGIS system.

Rip rap and large debris will be mechanically excavated from the existing RGIS sheet piling within the turbidity barrier area. The excavated material will be placed over the RGIS system and allowed to drain. Once sufficiently free of water, the excavated material will be transported to Dow's Salzburg Road Landfill for disposal. When all excavated material is properly disposed of, a layer of clean gravel will be placed over the length of the RGIS system.

Construction on the Geo-Tube containment cells and air monitoring stations will continue. Geo-Tubes and associated connections to the sediment transport line will be completed in preparation for dredging operations to start.

Next Steps

Once all rip rap and large debris are removed from the work area, installation of new permanent sheet piling for the RGIS system will begin. Dredging of contaminated sediment cannot begin until the permanent sheet piling is in place.

The second sheet piling crew will continue to install temporary sheet piling under the bridge. The temporary sheet piling will be installed along the entire length of the project area and will end adjacent to the Dow Dam.

Key Issues

U.S. EPA has completed its review and has provided comments to Dow on the Draft Work Plan for the site. Dow is preparing revisions and will resubmit changes by July 31, 2007.

U.S. EPA has completed its review of the site-specific Health and Safety Plan (HASP). Dow will incorporate U.S. EPA's recommendations into the HASP.

Cleanup in Region 5 | EPA Cleanup Home | Search CERCLIS database | Search NPL database


Local Navigation


Jump to main content.