POLREP #3 - 8/6/2007
On-Scene Coordinators - James Augustyn and Brian Schlieger

Site Description

On July 9, 2007, Dow's contractor began positioning equipment on a work barge to begin the preparation of driving temporary sheet piling in the river to delineate the area of highest dioxin contamination. Dow's contractor has completed construction on the HDPE sediment transport pipeline and has conducted hydrostatic testing of the line. The sediment transport line is approximately 9,000 feet long and will transport sediment slurry from the dredge area in the river to the Geo-Tube dewatering cell.

On-Scene Coordinators (OSC) Jim Augustyn and Brian Schlieger are providing oversight with assistance from U.S. EPA's START Contractor, Weston Solutions, Inc.

Current Activities

The following tasks have been completed by Dow's contractors during the period of July 28 to August 3, 2007:

Planned Removal Actions

Sheet piling will be driven down to established elevations to complete the installation of the turbidity barrier above the Dow bridge. Permanent Turbidity monitors will be placed in the river to monitory potential increases in turbidity that may result from excavation and dredging operations.

Rip rap and large debris will continue to be mechanically excavated from the existing RGIS sheet piling within the turbidity barrier area. The excavated material will be placed over the RGIS system and allowed to drain. Once sufficiently free of water, the excavated material will be transported to Dow's Salzburg Road Landfill for disposal.

Construction on the containment cell will continue. Geo-Tubes and associated connections to the sediment transport line will be completed in preparation for dredging operations to start.
Installation of the temporary turbidity barrier under the Dow bridge to the Dow Dam will continue.

Next Steps

Once all rip rap and large debris is removed from the work area, installation of new permanent sheet piling for the RGIS system will begin. Dredging of contaminated sediment cannot begin until the permanent sheet piling is in place. 

The second sheet piling crew will continue to install temporary sheet piling and will place another section under Dow's 'Railroad' bridge. The temporary sheet piling will be installed along the entire length of the project area and will end adjacent to the Dow Dam.