Jump to main content.


Reach D, Pollution Report 4

Tittabawassee River Dioxin-Reach D
Midland, MI - EPA Region V
POLREP #4 - 8/10/2007
On-Scene Coordinators - James Augustyn and Brian Schlieger

Site Description

On July 9, 2007, Dow's contractor began positioning equipment on a work barge to begin the preparation of driving temporary sheet piling in the river to delineate the area of highest dioxin contamination. Dow's contractor has completed construction on the HDPE sediment transport pipeline and has conducted hydrostatic testing of the line. The sediment transport line is approximately 9,000 feet long and will transport sediment slurry from the dredge area in the river to the Geo-Tube dewatering cell.

On-Scene Coordinators (OSC) Jim Augustyn and Brian Schlieger are providing oversight with assistance from U.S. EPA's START Contractor, Weston Solutions, Inc.

Current Activities

The following tasks have been completed by Dow's contractors during the period of August 04 to August 9th, 2007:

Planned Removal Actions

Next Steps

Once all remaining large debris and rip-rap is removed the installation of new permanent sheet piling for the RGIS system will begin. Dredging of contaminated sediment cannot begin until the permanent sheet piling is in place. 

A third sheet piling crew will be mobilized to the site. Two other piling crews will continue to install temporary sheet piling along the entire length of the project area and will end adjacent to the Dow Dam.

Key Issues

On Thursday evening August 9th, USEPA participated in the Community Meeting cosponsored by MDEQ and Dow Chemical in Saginaw, MI.

Disposition of Wastes

Waste consisted of Reach D rip-rap from the RGIS system. A total of 143 loads, estimated at 12 cubic yards per load total volume 1,716 estimated cubic yards

Cleanup in Region 5 | EPA Cleanup Home | Search CERCLIS database | Search NPL database


Local Navigation


Jump to main content.