Jump to main content.


Reach D, Pollution Report 5

Tittabawassee River Dioxin-Reach D
Midland, MI - EPA Region V
POLREP #5 - 8/16/2007
On-Scene Coordinators - James Augustyn and Brian Schlieger

Site Description

On July 9, 2007, Dow's contractor began positioning equipment on a work barge to begin the preparation of driving temporary sheet piling in the river to delineate the area of highest dioxin contamination. Dow's contractor has completed construction on the HDPE sediment transport pipeline and has conducted hydrostatic testing of the line. The sediment transport line is approximately 9,000 feet long and will transport sediment slurry from the dredge area in the river to the Geo-Tube dewatering cell.

On-Scene Coordinators (OSC) Jim Augustyn and Brian Schlieger are providing oversight with assistance from U.S. EPA's START Contractor, Weston Solutions, Inc.

Current Activities

The following tasks have been completed by Dow's contractors during the period of August 10 to August 16th, 2007:

Planned Removal Actions

Next Steps

Dow contractors will remove all historic 'flume' sheet piling and complete the installation of permanent sheet piling along the RGIS system. Dow's contractors will also install permanent upstream and downstream turbidity monitors.

Dredging of contaminated sediment cannot begin until the permanent sheet piling is installed and the permanent turbidity monitors have been staged.

Key Issues

The installation of two sections of gunderboom 'Turbidity Curtain' over a 30" and 36" underwater pipeline to complete temporary turbidity barrier

Disposition of Wastes

Waste consisted of Reach D rip-rap from the RGIS system. A total of 143 loads, estimated at 12 cubic yards per load total volume 1,716 estimated cubic yards

Cleanup in Region 5 | EPA Cleanup Home | Search CERCLIS database | Search NPL database


Local Navigation


Jump to main content.