Jump to main content.


Reach D, Pollution Report 8

Tittabawassee River Dioxin-Reach D
Midland, MI - EPA Region V
POLREP #8 - 9/12/2007
On-Scene Coordinators - James Augustyn and Brian Schlieger

Site Description

On July 9, 2007, Dow's contractor began positioning equipment on a work barge to begin the preparation of driving temporary sheet piling in the river to delineate the area of highest dioxin contamination. Dow's contractor has completed construction on the HDPE sediment transport pipeline and has conducted hydrostatic testing of the line. The sediment transport line is approximately 9,000 feet long and will transport sediment slurry from the dredge area in the river to the Geo-Tube dewatering cell.

On-Scene Coordinator (OSC) Jim Augustyn is providing oversight with assistance from U.S. EPA's START Contractor, Weston Solutions, Inc.

Current Activities

The following activities have been completed by Dow's contractors during the period of August 31st through Sept 12th, 2007. Routine tasks such as air monitoring, turbidity data collection from both upstream and downstream turbidity monitors, and 24-hour composite water sampling from the settling pond for total suspended solids (TSS) analysis are performed daily. Due to Labor Day Holiday, Dow contractors were inactive on Saturday Sept. 1st through Sept. 3rd, 2007. To view an aerial photo that depicts current site progress, please visit the Document Section of this website and open the document titled "Reach D Project Progress Figure".

Planned Removal Actions

Next Steps

Dow's contractors will continue driving the temporary sheet piling turbidity barrier from the Dow bridges downstream to the Dow Dam to complete the removal area.

The installation of two sections of gunderboom 'Turbidity Curtain' over a 30" and 36" underwater pipeline to complete temporary turbidity barrier south of downstream ‘railroad bridge'.

Disposition of Wastes

To date, 239 pieces (average length 10 to 12 feet) of historic flume piling have been extracted from the Reach D area north of the 'piping' bridge. The flume piling will be decontaminated and processed for metal reclamation.

Waste consisted of Reach D rip-rap from the RGIS system. A total of 154 loads, estimated at 12 cubic yards per load total volume 1,849 estimated cubic yards

From 9-06-07 to 9-11-07 Reach D sediment dewatering activities have conveyed 2,817,468.63 gallons of water to Dow's waste water treatment plant (WWTP).

Cleanup in Region 5 | EPA Cleanup Home | Search CERCLIS database | Search NPL database


Local Navigation


Jump to main content.