Reach D, Pollution Report 11

Tittabawassee River Dioxin-Reach D
Midland, MI - EPA Region V
POLREP #11 - 10/5/2007
On-Scene Coordinators - James Augustyn and Brian Schlieger

Site Description

On July 9, 2007, Dow's contractor began positioning equipment on a work barge to begin the preparation of driving temporary sheet piling in the river to delineate the area of highest dioxin contamination. Dow's contractor has completed construction on the HDPE sediment transport pipeline and has conducted hydrostatic testing of the line. The sediment transport line is approximately 9,000 feet long and will transport sediment slurry from the dredge area in the river to the Geo-Tube dewatering cell.

On-Scene Coordinator (OSC) Jim Augustyn is providing oversight with assistance from U.S. EPA's START Contractor, Weston Solutions, Inc.

Current Activities

The following activities have been completed by Dow's contractors during the period of September 25th through Oct 1st, 2007. Routine tasks such as dredging, raking of debris, excavation of sediment within contained turbidity barrier North of upstream ‘piping' bridge, stockpiling and dewatering of sediment in Northeast section of Reach D project area, air monitoring, turbidity data collection from both upstream and downstream turbidity monitors and 24-hour composite water sampling from the settling pond for total suspended solids (TSS) analysis are performed daily. To view an aerial photo that depicts current site progress, please visit the Document Section of this website and open the document titled "Reach D Project Progress Figure".

Planned Removal Actions

Next Steps

Dow's contractors will continue setting and driving the temporary sheet piling turbidity barrier to complete containment in the removal area.

The installation of two sections of gunderboom particulate containment system (PCS) 'Turbidity Curtain' over a 30" and 36" underwater pipeline to complete temporary turbidity barrier south of downstream ‘railroad bridge'.

Disposition of Wastes

To date, approximately 384 pieces (average length 10 to 12 feet) of historic flume piling have been extracted from the Reach D project area. The flume piling will be decontaminated and processed for metal reclamation.

Waste consisted of Reach D rip-rap, misc. debris and sediment from within the enclosed portion of the Northern Turbidity barrier containment north of the upstream ‘piping' bridge. A total of 266 loads, estimated at 12 cubic yards per load total volume 3,433 estimated cubic yards

From 9-06-07 to 9-29-07 Reach D sediment dewatering activities have conveyed 15,697,189 gallons of water to Dow's waste water treatment plant (WWTP).