Reach JK, Pollution Report 5

Tittabawassee River Dioxin-Reach D
Midland , MI - EPA Region V
POLREP #5 - 9/19/2007

On-Scene Coordinator - James Augustyn/Brian Schlieger

Site Description

On June 27, 2007, U.S. EPA ordered The Dow Chemical Company (Dow) to negotiate an Administrative Order on Consent, to address removal of extremely elevated levels of dioxin-contaminated soil from an eroding river bank within Reach JK of the Tittabawasse River near Midland, Michigan. Dow agreed to the terms of the Order and on July 12, 2007, the Order was signed by the Regional Administrator and Dow. For additional background information please see the site profile.

Reach JK will be divided into two areas. The area along the river bank where contaminated soil will be excavated will be designated JK-1, and an area further back from the river bank where clean soil will be used to cap contaminated soil will be designated JK-2.

On-Scene Coordinator (OSC) Jim Augustyn is providing oversight with assistance from U.S. EPA's START Contractor, Weston Solutions, Inc.

Current Activities

The following tasks are currently on going:

The following tasks have been completed by Dow's contractor during the period from August 31 - September 12, 2007:

Planned Removal Actions

The following tasks will be implemented:

Next Steps

Awaiting comments from the Trustees on the Restoration Work Plan to finalize seed slection for ground cover.

Disposition of Wastes

As of 9/12/07, Dow has removed and transported to the landfill approximately 23,562 in-place cubic yards of impacted soil from the Reach JK site. Approximately 24,000 in-place cubic yards of impacted soil was the estimated total volume to be removed. The following disposed waste was excavated from the JK-1 Cut #1 area: