Region 3
Early Action Compact Details
Maryland
Early Action Compact
Washington County
(west of Washington, DC)
|
Early Action Compact area map |
|
Early Action Compact submitted to
EPA |
|
Response letters from EPA |
|
November 5, 2004 ... Draft of
State Implementation Plan for Early Action Compact
area |
| Milestones |
| |
|
June 16, 2003
... Submitted list of potential local control
measures being considered in local planning
process |
|
March 31, 2004
... The local plan, including final list of
local control measures and technical support
information, submitted to the State for
inclusion in the SIP |
|
| Progress
Reports |
| |
|
June 30, 2003
... Submitted 1st semiannual progress report
covering the period January-June 2003 |
|
December 31, 2003
... Submitted 2nd semiannual progress
report covering the period July-December
2003 |
|
December 31, 2005
... Submitted 6th semiannual progress
report covering the period July-December
2005 |
|
June 30, 2006
... Submitted 7th semiannual progress report
covering the period January-June 2006 |
|
December 31, 2006
... Submitted 8th semiannual progress report
covering the period July-December 2006 |
|
June 30, 2007 ... Submitted 9th semiannual progress report
covering the period January-June 2007 |
|
| |
Virginia
Early Action Compact
Northern Shenandoah Valley Region
(Winchester area)
|
Early Action Compact area map |
|
Early Action Compact submitted to
EPA |
|
Response letters from EPA |
|
November 23, 2004 ... Draft of
State Implementation Plan for Early Action Compact
area |
| Milestones |
| |
|
June 16, 2003
... Submitted list of potential local control
measures being considered in local planning
process |
|
March 31, 2004
... The local plan, including final list of
local control measures and technical support
information, submitted to the State for
inclusion in the SIP |
|
| Progress
Reports |
| |
|
June 30, 2003
... Submitted 1st semiannual progress report
covering the period January-June 2003 |
|
December 31, 2003
... Submitted 2nd semiannual progress
report covering the period July-December
2003 |
|
June 30, 2004
... Submitted 3rd semiannual progress report
covering the period January-June 2004 |
|
December 31, 2005
... Submitted 6th semiannual progress
report covering the period July-December
2005 |
|
June 30, 2006
... Submitted 7th semiannual progress report
covering the period January-June 2006 |
|
December 31, 2006
... Submitted 8th semiannual progress report
covering the period July-December 2006 |
|
June 30, 2007 ... Submitted 9th semiannual progress report
covering the period January-June 2007 |
|
|
Virginia
Early Action Compact
Roanoke Area
|
Early Action Compact area map |
|
Early Action Compact submitted to
EPA |
|
Response letters from EPA |
|
November 23, 2004 ... Draft of
State Implementation Plan for Early Action Compact
area |
| Milestones |
| |
|
June 16, 2003
... Submitted list of potential local control
measures being considered in local planning
process |
|
March 31, 2004
... The local plan, including final list of
local control measures and technical support
information, submitted to the State for
inclusion in the SIP |
|
| Progress
Reports |
| |
|
June 30, 2003
... Submitted 1st semiannual progress report
covering the period January-June 2003 |
|
December 31, 2003
... Submitted 2nd semiannual progress
report covering the period July-December
2003 |
|
June 30, 2004
... Submitted 3rd semiannual progress report
covering the period January-June 2004 |
|
December 31, 2005
... Submitted 6th semiannual progress
report covering the period July-December
2005 |
|
June 30, 2006
... Submitted 7th semiannual progress report
covering the period January-June 2006 |
|
December 31, 2006
... Submitted 8th semiannual progress report
covering the period July-December 2006 |
|
June 30, 2007 ... Submitted 9th semiannual progress report
covering the period January-June 2007 |
|
| |
West Virginia
Early Action Compact
The Eastern Pan Handle Region
(Martinsburg area )
|
Early Action Compact area map |
|
Early Action Compact submitted to
EPA |
|
Response letters from EPA |
|
November 18, 2004 ... Draft of
State Implementation Plan for Early Action Compact
area |
| Milestones |
| |
|
June 16, 2003
... Submitted list of potential local control
measures being considered in local planning
process |
|
March 31, 2004
... The local plan, including final list of
local control measures and technical support
information (document now included
here on August 12, 2004),
submitted to the State for inclusion in the
SIP |
|
| Progress
Reports |
| |
|
June 30, 2003
... Submitted 1st semiannual progress report
covering the period January-June 2003 |
|
December 31, 2005
... Submitted 6th semiannual progress
report covering the period July-December
2005 |
|
June 30, 2006
... Submitted 7th semiannual progress report
covering the period January-June 2006 |
|
December 31, 2006
... Submitted 8th semiannual progress report
covering the period July-December 2006 |
|
June 30, 2007 ... Submitted 9th semiannual progress report
covering the period January-June 2007 |
|
| |
|