Skip to main content
U.S. flag

An official website of the United States government

Here’s how you know

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock (LockA locked padlock) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

    • Environmental Topics
    • Air
    • Bed Bugs
    • Cancer
    • Chemicals, Toxics, and Pesticide
    • Emergency Response
    • Environmental Information by Location
    • Health
    • Land, Waste, and Cleanup
    • Lead
    • Mold
    • Radon
    • Research
    • Science Topics
    • Water Topics
    • A-Z Topic Index
    • Laws & Regulations
    • By Business Sector
    • By Topic
    • Compliance
    • Enforcement
    • Laws and Executive Orders
    • Regulations
    • Report a Violation
    • Environmental Violations
    • Fraud, Waste or Abuse
    • About EPA
    • Our Mission and What We Do
    • Headquarters Offices
    • Regional Offices
    • Labs and Research Centers
    • Planning, Budget, and Results
    • Organization Chart
    • EPA History

Breadcrumb

  1. Home
  2. News Releases

EPA Proposes Interim Plan to Address Groundwater Contamination at the Welsbach/General Gas Mantle Superfund Site in Gloucester City and Camden, N.J.

August 24, 2021

Contact Information
Stephen McBay (mcbay.stephen@epa.gov)
212-637-3672

NEW YORK – The U.S. Environmental Protection Agency (EPA) has proposed an interim plan to address groundwater contaminated with radium at the Welsbach/General Gas Mantle Superfund site located in Camden and Gloucester City, New Jersey. EPA is taking public comment on its plan and will host a virtual public meeting on September 8.

“This proposed plan continues EPA’s work to protect residents of Gloucester City and Camden from contamination associated with this site. Having already taken many actions to address the source of contamination, in this case we are focusing on contaminated groundwater,” said Acting Regional Administrator Walter Mugdan. “This is an interim plan that we propose to implement as we continue to assess the groundwater to see if we need to do more to address it in the long term. We feel this interim plan is the best approach and we look forward to continue to work closely with the impacted communities.”

EPA is proposing an interim cleanup plan, called a remedy, which will allow natural processes to break down radioactive elements in the groundwater into less harmful substances, coupled with putting into place institutional controls, such as restrictions on the use of the impacted groundwater, and conducting long-term monitoring of the groundwater to ensure that the breakdown of radioactive elements is happening as anticipated. EPA reached its decision based on information including results of the sampling of the groundwater between 2018 and 2020.

This Welsbach/General Gas Mantle Superfund site is divided into four phases of work called operable units, which are discrete pieces of the wider cleanup effort. This proposed plan addresses the fourth operable unit (OU4), which is groundwater. Under a cleanup plan for operable unit 1 (OU1) EPA is currently addressing radiologically impacted soil in the study area in Gloucester City, New Jersey. The interim remedy proposed today would be implemented during the OU1 cleanup of the radiologically contaminated soil. Once that soil, which is a source of groundwater contamination, is fully addressed the interim groundwater remedy will be reevaluated and EPA will establish a permanent groundwater cleanup plan.

EPA completed the cleanup work for OU2 in 2017, which included decontaminating building surfaces at the Armstrong Building (the last remaining building from Welsbach's gas mantle operations) and disposing of the radiologically contaminated soil/waste to an approved off-site location. After careful study, EPA determined that no cleanup action was needed for OU3, which includes wetlands, surface water, and sediment as they posed no radiological threat to people or the environment.

EPA will continue to monitor the groundwater and will conduct a review of the site conditions at least every five years to ensure the effectiveness of the interim remedy. Work under today’s proposed plan is estimated to cost $460,000.

The EPA will hold a virtual public meeting to discuss its proposed interim plan on September 8, 2021, at 6:00 pm. To register for the public meeting, please visit https://welsbach-ggm.eventbrite.com.

Written comments on the proposed plan, postmarked no later than close of business September 24, 2021, can be mailed or emailed to Thomas Dobinson, Remedial Project Manager, U.S. Environmental Protection Agency, 290 Broadway – 19th Floor, New York, NY 10007, Email: dobinson.thomas@epa.gov

For site background and to view the proposed interim plan, visit: https://www.epa.gov/superfund/welsbach-ggm

Follow EPA Region 2 on Twitter at http://twitter.com/eparegion2 and visit our Facebook page, http://facebook.com/eparegion2

21-052

Related Links

  • Region 02
  • Read other EPA News Releases about Superfund and Brownfields
  • Read other EPA News Releases about Water
Contact Us about News Releases
Contact Us about News Releases to ask a question, provide feedback, or report a problem.
Last updated on August 3, 2023
  • Assistance
  • Spanish
  • Arabic
  • Chinese (simplified)
  • Chinese (traditional)
  • French
  • Haitian Creole
  • Korean
  • Portuguese
  • Russian
  • Tagalog
  • Vietnamese
United States Environmental Protection Agency

Discover.

  • Accessibility Statement
  • Budget & Performance
  • Contracting
  • EPA www Web Snapshot
  • Grants
  • No FEAR Act Data
  • Plain Writing
  • Privacy
  • Privacy and Security Notice

Connect.

  • Data
  • Inspector General
  • Jobs
  • Newsroom
  • Regulations.gov
  • Subscribe
  • USA.gov
  • White House

Ask.

  • Contact EPA
  • EPA Disclaimers
  • Hotlines
  • FOIA Requests
  • Frequent Questions
  • Site Feedback

Follow.