Report: Lack of Project Plan Resulted in Transition and Contractor Performance Problems for the Institutional Controls Tracking System

Report #09-P-0128March 25, 2009

What Was Found

Lack of compliance with established project management procedures resulted in transitional problems in 2005 that delayed ICTS development and negatively affected contractor performance.