§52.2520 Identification of plan.
(d) EPA-Approved Source Specific Requirements
Source name | Permit/order or registration number | State effective date |
EPA approval date | Additional explanation/ citation at 40 CFR 52.2565 |
---|---|---|---|---|
National Steel Corp.—Weirton Steel Division | Consent Order (Bubble) | 7/6/82 | 12/9/82 47 FR 55396 | (c)(19). |
Columbia Gas Transmission Corporation—Lost River Station | Consent Order | 9/12/90 | 4/24/91 56 FR 18733 | (c)(24). |
Wheeling-Pittsburgh Steel Corp | Consent Order CO-SIP-91-29 | 11/14/91 | 7/25/94 59 FR 37696 | (c)(26). |
Koppers Industries, Inc | Consent Order CO-SIP-91-32 | 11/14/91 | 7/25/94 59 FR 37696 | (c)(26). |
Starvaggi Industries, Inc | Consent Order CO-SIP-91-34 | 11/14/91 | 7/25/94 59 FR 37696 | (c)(26). |
Quaker State Corporation | Consent Order CO-SIP-95-1 | 1/9/95 | 11/27/96 61 FR 60191 | (c)(35). |
Weirton Steel Corporation | Consent Order CO-SIP-95-2 | 1/9/95 | 11/27/96 61 FR 60191 | (c)(35). |
PPG Industries, Inc | Consent Order CO-SIP-2000-1 | 1/25/00 | 8/2/00 65 FR 47339 | (c)(44)(i)(B)(1). |
Bayer Corporation | Consent Order CO-SIP-2000-2 | 1/26/00 | 8/2/00 65 FR 47339 | (c)(44)(i)(B)(2). |
PPG Industries, Inc | Consent Order CO-SIP-C-2003-27 | 7/29/03 | 4/28/04 69 FR 23110 | (c)(58). |
Wheeling-Pittsburgh Steel Corporation | Operating Permit R13-1939A | 8/19/03 | 05/05/04 69 FR 24986 | (c)(59)(i)(B)(1). |
Weirton Steel Corporation | Consent Order, CO-SIP-C-2003-28 | 8/4/03 | 05/05/04 69 FR 24986 | (c)(59)(i)(B)(2). |
Mountain State Carbon | Consent Order CO-SIP-C-2017-9 | 9/29/17 | 10/22/19 84 FR 56385 | |
Mitchell Power Plant (pdf) | Consent Order CO-SIP-C-2019-13 | 01/01/2020 |
10/26/2020 85 FR 67664 |
Established SO2 emission limit. |
[70 FR 7027, Feb. 10, 2005]
Editorial Note: For Federal Register citations affecting §52.2520, see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and at www.fdsys.gov.