Skip to main content
U.S. flag

An official website of the United States government

Here’s how you know

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock (LockA locked padlock) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

    • Environmental Topics
    • Air
    • Bed Bugs
    • Cancer
    • Chemicals, Toxics, and Pesticide
    • Emergency Response
    • Environmental Information by Location
    • Health
    • Land, Waste, and Cleanup
    • Lead
    • Mold
    • Radon
    • Research
    • Science Topics
    • Water Topics
    • A-Z Topic Index
    • Laws & Regulations
    • By Business Sector
    • By Topic
    • Compliance
    • Enforcement
    • Laws and Executive Orders
    • Regulations
    • Report a Violation
    • Environmental Violations
    • Fraud, Waste or Abuse
    • About EPA
    • Our Mission and What We Do
    • Headquarters Offices
    • Regional Offices
    • Labs and Research Centers
    • Planning, Budget, and Results
    • Organization Chart
    • EPA History

Breadcrumb

  1. Home
  2. Air Quality Implementation Plans

Texas SIP: 30 TAC 117.520. Compliance Schedule For Commercial, Institutional, and Industrial Combustion Sources; SIP effective 2000.04.03

Regulatory Text: 
§117.520.  Compliance Schedule For Commercial, Institutional, and Industrial Combustion Sources.

(Approved by EPA 03/03/2000 (65 FR 11468) effective 04/03/2000.)

     All persons affected by the provisions of §§117.201, 117.203, 117.205, 117.207-117.209, 117.211, 117.213, 117.215, 117.217, 117.219, 117.221, and 117.223 of this title (relating to Commercial, Institutional, and Industrial Sources) shall be in compliance as soon as practicable, but no later than November 15, 1999 (final compliance date).  All affected persons shall meet the following compliance schedules and submit written notification to the executive director:

          (1)  submit a plan for compliance in accordance with §117.209 of this title (relating to Initial Control Plan Procedures) according to the following schedule:

               (A)  for major sources of nitrogen oxides (NOx) which have units subject to emission specifications under this chapter, submit an initial control plan for all such units no later than April 1, 1994;

               (B)  for major sources of NOx which have no units subject to emission specifications under this chapter, submit an initial control plan for all such units no later than September 1, 1994; and

               (C)  for major sources of NOx subject to either subparagraphs (A) or (B) of this paragraph, submit the information required by §117.209(c)(6), (7), and (9) of this title no later than September 1, 1994;

          (2)  install all NOx abatement equipment and implement all NOx control techniques no later than November 15, 1999;

          (3)  for units operating without continuous emissions monitoring system (CEMS) or predictive emissions monitoring systems (PEMS), conduct applicable tests for initial demonstration of compliance as specified in §117.211 of this title (relating to Initial Demonstration of Compliance); and submit the results by April 1, 1994, or as early as practicable, but in no case later than November 15, 1999;

          (4)  for units operating with CEMS or PEMS and complying with the NOx emission limit on a rolling 30-day average, conduct the applicable tests for the initial demonstration of compliance as specified in §117.211 of this title and submit the results of the applicable CEMS or PEMS performance evaluation and quality assurance procedures as specified in §117.213 of this title (relating to Continuous Demonstration of Compliance) no later than January 15, 2000;

          (5)  for units operating with CEMS or PEMS and complying with the NOx emission limit in pounds per hour on a block one-hour average, conduct the applicable tests for the initial demonstration of compliance as specified in §117.211 of this title and submit the results of the applicable CEMS or PEMS performance evaluation and quality assurance procedures as specified in §117.213 of this title by November 15, 1999; and

          (6)  no later than November 15, 1999, submit a final control plan for compliance in accordance with §117.215 of this title (relating to Final Control Plan Procedures).

As adopted by TNRCC May 20, 1998 effective June 10, 1998

************************* end tx 117.520 ********************ea43**a3r**

Air Quality Implementation Plans

  • About Air Quality Implementation Plans
  • Approved Air Quality Implementation Plans
  • Develop an Air Quality SIP
  • Find a Regional Contact for Air Quality SIPs/FIPS/TIPs
  • Tools for SIP Status
Contact Us about Air Quality Implementation Plans
Contact Us to ask a question, provide feedback, or report a problem.
Last updated on January 8, 2025
  • Assistance
  • Spanish
  • Arabic
  • Chinese (simplified)
  • Chinese (traditional)
  • French
  • Haitian Creole
  • Korean
  • Portuguese
  • Russian
  • Tagalog
  • Vietnamese
United States Environmental Protection Agency

Discover.

  • Accessibility Statement
  • Budget & Performance
  • Contracting
  • EPA www Web Snapshot
  • Grants
  • No FEAR Act Data
  • Plain Writing
  • Privacy
  • Privacy and Security Notice

Connect.

  • Data
  • Inspector General
  • Jobs
  • Newsroom
  • Regulations.gov
  • Subscribe
  • USA.gov
  • White House

Ask.

  • Contact EPA
  • EPA Disclaimers
  • Hotlines
  • FOIA Requests
  • Frequent Questions
  • Site Feedback

Follow.