Skip to main content
U.S. flag

An official website of the United States government

Here’s how you know

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock (LockA locked padlock) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

    • Environmental Topics
    • Air
    • Bed Bugs
    • Cancer
    • Chemicals, Toxics, and Pesticide
    • Emergency Response
    • Environmental Information by Location
    • Health
    • Land, Waste, and Cleanup
    • Lead
    • Mold
    • Radon
    • Research
    • Science Topics
    • Water Topics
    • A-Z Topic Index
    • Laws & Regulations
    • By Business Sector
    • By Topic
    • Compliance
    • Enforcement
    • Laws and Executive Orders
    • Regulations
    • Report a Violation
    • Environmental Violations
    • Fraud, Waste or Abuse
    • About EPA
    • Our Mission and What We Do
    • Headquarters Offices
    • Regional Offices
    • Labs and Research Centers
    • Planning, Budget, and Results
    • Organization Chart
    • EPA History

Breadcrumb

  1. Home
  2. Air Quality Implementation Plans

Louisiana LAC 33:III Ch. 5 Section 519 - Permit Issuance Procedures for New Facilities, Initial Permits, Renewals and Significant Modifications, SIP effective September 6, 2016 (LAd51)

Regulatory Text:
Louisiana Administrative Code, Title 33 ENVIRONMENTAL QUALITY, Part III Air (LAC 33:III)

Chapter 5.  Permit Procedures

Section 519. Permit Issuance Procedures for New Facilities, Initial Permits, Renewals and Significant Modifications.
As approved by EPA August 4, 2016 (81 FR 51341) SIP effective September 6, 2016 (LAd51),
Regulations.gov docket EPA-R06-OAR-2014-0821 [LA048].
NOT IN SIP: LAC 33:III.519.C

Updated with revisions adopted in the Louisiana Register November 20, 1993, LR19:1420 (AQ70), 
submitted to EPA November 15, 1993 (LA-017), Regulations.gov document EPA-R06-OAR-2014-0821-0003 [LA048.03A].
AQ70 §519;LAd51;LA048.03A;AQ70;LR19:1420(11/20/1993), submitted to EPA November 15, 1993.

   A. Completeness Review
      1. Within 60 days of receipt of a permit application, the permitting authority shall review the application for completeness and shall:
         a. notify the applicant in writing that the application is complete; or
         b. notify the applicant in writing of any deficiencies.
      2. The applicant shall submit any additional information requested by the date specified in such notice. Pursuant to LAC 33:I.Chapter 15, for any application pertaining to a new facility or to a substantial permit modification, the date specified for submittal shall be no later than 30 days from receipt of the notice of deficiency.
      3. If the permitting authority fails to issue a notice of completeness or deficiency within 60 days from receipt of the application or receipt of additional information requested under Subsection A.1 of this Section, the application shall be deemed complete.
      4. Pursuant to LAC 33:I.Chapter 15, for any application pertaining to a new facility which will be a major source or to a substantial permit modification, the applicant shall publish a notice of the completeness determination in a major local newspaper.
   B. Technical Review
      1. If at any time during the review process of an application that has been determined or deemed to be complete the permitting authority determines that additional information is necessary to evaluate or take final action on the application, the permitting authority shall provide notice to the applicant and require a response within a reasonable specified time.
      2. The applicant shall respond to the notice within the time specified. Such response shall contain all information requested by the permitting authority and required to complete the technical review.
   C. NOT IN SIP

***End Louisiana LAC 33:III Ch. 5 Section 519 - Permit Issuance Procedures for New Facilities, Initial Permits, Renewals and Significant Modifications, SIP effective September 6, 2016 (LAd51)***

Air Quality Implementation Plans

  • About Air Quality Implementation Plans
  • Approved Air Quality Implementation Plans
  • Develop an Air Quality SIP
  • Find a Regional Contact for Air Quality SIPs/FIPS/TIPs
  • Tools for SIP Status
Contact Us about Air Quality Implementation Plans
Contact Us to ask a question, provide feedback, or report a problem.
Last updated on February 12, 2025
  • Assistance
  • Spanish
  • Arabic
  • Chinese (simplified)
  • Chinese (traditional)
  • French
  • Haitian Creole
  • Korean
  • Portuguese
  • Russian
  • Tagalog
  • Vietnamese
United States Environmental Protection Agency

Discover.

  • Accessibility Statement
  • Budget & Performance
  • Contracting
  • EPA www Web Snapshot
  • Grants
  • No FEAR Act Data
  • Plain Writing
  • Privacy
  • Privacy and Security Notice

Connect.

  • Data
  • Inspector General
  • Jobs
  • Newsroom
  • Regulations.gov
  • Subscribe
  • USA.gov
  • White House

Ask.

  • Contact EPA
  • EPA Disclaimers
  • Hotlines
  • FOIA Requests
  • Frequent Questions
  • Site Feedback

Follow.