Florida Proposed Title V Permits

The following permits have been submitted to EPA Region 4 as Proposed Title V permits. While EPA has the right to a 45-day review period for all Proposed Title V permits, EPA Region 4 targets only a subset of these permits for comprehensive review. To find out which permits have been targeted for EPA Region 4 review, please contact the Region 4 staff person(s) listed at the bottom of this page.



Title V Permits Undergoing Sequential Review**
State County Source Name PA Permit Number 45-Day Review Ends (parallel) Petition Deadline
FL Brevard Vectorworks Merritt Island 0090235008AV 8/24/2018 10/23/2018
FL Broward Transmontaigne - Port Everglades Terminal 0110053012AV 9/13/2018 11/12/2018
FL Broward FP&L - Fort Lauderdale Power Plant 0110037019AV 9/16/2018 11/15/2018
FL St. Lucie Florida Municipal Power Agency - Treasure Coast Energy Center 1110121010AV 9/17/2018 11/16/2018
FL Volusia FPC - Debray Facility 1270028014AV 9/29/2018 11/28/2018
FL Alachua GRU - J. R. Kelly Generating Station 0010005013AV 10/8/2018 12/7/2018
FL Santa Rosa FABBRO MARINE GROUP 1131135002AV 10/19/2018 12/18/2018
FL Duval JEA - Brandy Branch 0310485023AV 10/22/2018 12/21/2018
FL Sumter ACMS Sumter Solid Waste Class I Landfill 1190053005AV 11/11/2018 1/10/2019
FL Duval JEA-Northside Generating Stn & St.Johns River Power Park (NGS/SJRPP) 0310045052AV 11/12/2018 1/11/2019
FL Miami-Dade FP&L - TURKEY POINT POWER PLANTS 0250003030AV 11/15/2018 1/14/2019
FL St. Lucie St. Lucie Co. - Glades Road Landfill 1110081010AV 11/16/2018 1/15/2019


Title V Permits Undergoing Parallel Review**
State County Source Name PA Permit Number 45-Day Review Ends (parallel) Petition Deadline
FL Polk Keymark Corp. of Florida 1050320020AV 7/14/2018 10/19/2018

* Sequential Review means the EPA 45-day review period does not begin until the 30-day public comment period ends. The deadline for the public to petition EPA is 60 days after the EPA 45-day review period ends.

** Parallel Review means the EPA 45-day review period runs concurrently with the 30-day public comment period and ends no earlier than 15 days after the end of the public comment period. The deadline for the public to petition EPA is 60 days after the EPA 45-day review period ends, calculated as if the Title V permit was under sequential review (i.e., the petition deadline will be the same regardless of whether Parallel or Sequential Review is followed.)

For information about the contents of this page please contact Ana Oquendo-Vazquez.