Georgia Proposed Title V Permits

The following permits have been submitted to EPA Region 4 as Proposed Title V permits. While EPA has the right to a 45-day review period for all Proposed Title V permits, EPA Region 4 targets only a subset of these permits for comprehensive review. To find out which permits have been targeted for EPA Region 4 review, please contact the Region 4 staff person(s) listed at the bottom of this page.



Title V Permits Undergoing Sequential Review**
State County Source Name PA Permit Number 45-Day Review Ends (sequential) Petition Deadline
           


Title V Permits Undergoing Parallel Review**
State County Source Name PA Permit Number 45-Day Review Ends (parallel) Petition Deadline
GA Lee Woodgrain Millwork, Inc. 2431-177-0010-V-05-0 11/24/2018 2/22/2019
GA Appling Appling County Pellets LLC 2499-001-0032-V-02-0 11/24/2018 2/22/2019
GA Thomas Beadles & Balfour, LLC 2421-275-0022-V-07-0 11/26/2018 2/25/2019
GA Bartow Gerdau Ameristeel US Inc. 3312-015-0032-V-06-0 12/2/2018 3/2/2019
GA Ben Hill West Fraser Fitzgerald Lumber Mill 2421-017-0008-V-05-1 12/15/2018 3/15/2019
GA Effingham Georgia Power Company - Plant McIntosh 4911-103-0003-V-04-0 12/15/2018 3/15/2019
GA Bibb Cherokee Brick & Tile Company 3251-021-0167-V-04-1 12/18/2018 3/18/2019
GA Ware Georgia Biomass LLC 2499-299-0053-V-03-0 12/22/2018 3/22/2019
GA Mitchell Baconton Power LLC 4911-205-0044-V-06-0 12/29/2018 3/29/2019
GA Mitchell SOWEGA Power LLC 4911-205-0043-V-09-0 12/29/2018 3/29/2019
GA Fulton R. M. Clayton Water Reclamation Center 4952-121-0268-V-03-0 12/30/2018 3/30/2019
GA Effingham Georgia Power Company - McIntosh Combined Cycle Facility 4911-103-0014-V-05-1 1/5/2019 4/5/2019
GA Wilkinson Carbo Ceramics, Inc. - McIntyre Plant 3295-319-0027-V-05-0 1/20/2019 4/20/2019
GA Heard Georgia Power Company - Plant Wansley 4911-149-0001-V-04-0 1/26/2019 4/26/2019
GA Dougherty Albany Green Energy, LLC 4911-095-0109-V-01-5 1/30/2019 4/30/2019
GA Crisp Norbord Georgia, Inc. 2493-081-0054-V-05-0 2/5/2019 5/6/2019
GA Upson Edward L. Addison Generating Plant 4911-293-0027-V-05-0 2/9/2019 5/10/2019
GA Camden Naval Submarine Base 9711-039-0003-V-04-0 2/10/2019 5/11/2019
GA Liberty Fort Stewart Hqs 3rd Infrantry Division (Mechanized) 9711-179-0018-V-03-2 2/12/2019 5/13/2019
GA Richmond Kemira Chemicals Inc 2819-245-0138-V-05-0 2/11/2019 5/13/2019
GA Dougherty The Procter & Gamble Paper Products Co. 2676-095-0071-V-04-0 2/11/2019 5/13/2019
GA Laurens West Fraser - Dudley Lumber Mill 2421-175-0035-V-05-1 2/26/2019 5/27/2019
GA Floyd Georgia-Pacific Wood Products South LLC – Lumber Plant 2421-115-0016-V-05-1 3/15/2019 6/13/2019
GA Liberty Interstate Paper LLC 2631-179-0001-V-04-2 3/16/2019 6/14/2019
GA Ben Hill Agri-Products, Inc. 2499-017-0041-V-05-0 3/16/2019 6/14/2019
GA Terrell Golden Peanut Company, LLC 2076-273-0022-V-05-0 3/17/2019 6/15/2019
GA Houston Interfor U.S. Inc 2421-153-0011-V-05-1 3/30/2019 6/28/2019

* Sequential Review means the EPA 45-day review period does not begin until the 30-day public comment period ends. The deadline for the public to petition EPA is 60 days after the EPA 45-day review period ends.

** Parallel Review means the EPA 45-day review period runs concurrently with the 30-day public comment period and ends no earlier than 15 days after the end of the public comment period. The deadline for the public to petition EPA is 60 days after the EPA 45-day review period ends, calculated as if the Title V permit was under sequential review (i.e., the petition deadline will be the same regardless of whether Parallel or Sequential Review is followed.)