Tennessee Proposed Title V Permits

The following permits have been submitted to EPA Region 4 as Proposed Title V permits. While EPA has the right to a 45-day review period for all Proposed Title V permits, EPA Region 4 targets only a subset of these permits for comprehensive review. To find out which permits have been targeted for EPA Region 4 review, please contact the Region 4 staff person(s) listed at the bottom of this page.



Title V Permits Undergoing Sequential Review**
State County Source Name PA Permit Number 45-Day Review Ends (sequential) Petition Deadline
TN Roane TVA- Kingston Fossil Plant 572149 1/6/2018 3/7/2018
TN Shelby K.T.G. (USA) LP 00190-01TV 1/18/2018 3/19/2018
TN Shelby Solae, LLC 0279-01TV 2/22/2018 4/23/2018
TN Davidson Columbia Gulf Transmission, LLC 3/23/2018 5/22/2018


Title V Permits Undergoing Parallel Review**
State County Source Name PA Permit Number 45-Day Review Ends (parallel) Petition Deadline
TN - Parallel
TN Marshall East Tennessee Natural Gas, LLC - Station 3206 572002 11/25/2017 2/26/2018
TN Lincoln Goodman Company, L.P. 566422 11/25/2017 2/26/2018
TN Roane TVA- Kingston Fossil Plant 572149 9/28/2017 3/7/2018
TN Obion Titan Tire Corporation 470506 12/11/2017 3/12/2018
TN Anderson Oak Ridge Y-12 National Security Complex 571832 12/17/2017 3/16/2018
TN Cheatham State Industries, Inc. 562496 12/16/2017 3/16/2018
TN Obion Northwest Tennessee Disposal Corporation 571770 12/30/2017 3/22/2018
TN Hardeman Tennessee Gas Pipeline Company, L.L.C. (TGP) - Station 71 572606 1/18/2018 4/6/2018
TN Stewart TVA - Cumberland Fossil Plant - 81-0011 562460 1/12/2018 4/12/2018
TN Sullivan Eastman Chemical Company (MSOP)-32 568496 1/22/2018 4/23/2018
TN Sullivan Eastman Chemical Company (82-0003) MSOP-27 567681 1/22/2018 4/23/2018
TN Humphreys The Chemours Company 569782 1/27/2018 4/30/2018
TN Blount Arconic Inc.- South Plant Reclamation 572135 2/24/2018 5/25/2018
TN Shelby CCL-Korsini, LLC 01256-01P 3/23/2018 6/15/2018
TN Madison Foam Fabricators, Inc. 572557 3/23/2018 6/21/2018
TN Weakly Meridian Brick LLC 572182 3/24/2018 6/23/2018
TN Knox University of Tennessee 566694 3/30/2018 6/28/2018

* Sequential Review means the EPA 45-day review period does not begin until the 30-day public comment period ends. The deadline for the public to petition EPA is 60 days after the EPA 45-day review period ends.

** Parallel Review means the EPA 45-day review period runs concurrently with the 30-day public comment period and ends no earlier than 15 days after the end of the public comment period. The deadline for the public to petition EPA is 60 days after the EPA 45-day review period ends, calculated as if the Title V permit was under sequential review (i.e., the petition deadline will be the same regardless of whether Parallel or Sequential Review is followed.)

For information about the contents of this page please contact Eva Land


Top of Page