New Bedford Harbor

General Information about the New Bedford Harbor Cleanup

You may need a PDF reader to view some of the files on this page. See EPA’s About PDF page to learn more.
On this page:

Site Description and History

The 18,000-acre New Bedford site is an urban tidal estuary with sediments which are highly contaminated with polychlorinated biphenyls (PCBs) and heavy metals. At least two manufacturers in the area used PCBs while producing electric devices from the 1940 to the late 1970s. These facilities discharged industrial wastes containing PCBs directly into the harbor and indirectly through the city sewer system. This stopped when the manufacture of PCBs was banned by EPA. As a result, the harbor was contaminated with PCBs in varying degrees for at least 6 miles from the upper Acushnet River into Buzzards Bay. Over 100,000 people live within 3 miles of the site.This site is being addressed in four stages: initial actions and three long-term remedial phases focusing on the hot spot area, the upper and lower harbor areas, and the outer harbor Buzzards Bay area.Bioaccumulation of PCBs within the marine food chain has resulted in closing certain areas areas to lobstering, shellfishing, and fishing; in other areas the frequency of fish and shellfish meals are subject to advisories. Since 1982, signs warning the public of the presence of PCBs in the harbor have been in place and maintenance and replacement of these continue as needed.

Top of Page


What progress is being made?

When the cleanup began, the areas with the highest levels of PCBs were addressed first. A 5-acre northern portion of the Acushnet River estuary was identified as the "hot spot" area (about 14,000 yd3 of sediment exceeding a concentration of about 4,000 mg/kg total PCB) and addressed prior to the start of the full scale dredging in the upper and lower harbor. This cleanup took place from 1994 to 1995 and the off-site disposal of the resulting highly contaminated material was completed in 2000.

An annual program of subtidal dredging was conducted starting in 2004 with ;about $15M in annual funds provided by EPA’s Superfund program throughout the Upper Harbor, north of Coggeshall Street Bridge.

In 2013, additional funding for the cleanup was secured under a $366.25 million settlement reached with a major responsible party. The settlement made acceleration in pace of the cleanup possible, starting in 2014.

Subtidal Dredging: Now Complete

Approximately 600,000 cubic yards of PCB-contaminated sediment from the Upper Harbor was dredged and disposed off-site in a secure landfill. This portion of the cleanup was completed in 2019. About 388,000 cubic yards of PCB contaminated sediment from the Lower Harbor and lower portion of the Upper Harbor was dredged followed by disposal in the Lower Harbor CAD Cell. This operation was completed between 2016 and ;March 2020.

In total, over several decades, about 1 million cubic yards of PCB contaminated material was dredged from the Harbor by the Superfund program.

Interim Sediment Cap at Aerovox: Complete

The highly contaminated Aerovox former mill on Belleville Avenue in New Bedford is being addressed under the Massachusetts Chapter 21E site cleanup program. EPA has constructed an interim sediment cap in a 3 acre area subtidal adjoining the Aerovox facility shown on the attached map. Construction of the interim sediment cap in 2018-2019 allowed EPA’s final pass dredging to proceed ahead of the ongoing state Aerovox site cleanup which was still at a preliminary stage. The interim sediment cap will prevent underlying PCBs (polychlorinated biphenyls) and VOCs (volatile organic compounds, i.e., solvents) from the Aerovox Site from re-contaminating the newly dredged adjacent river sediments in the Harbor. Once complete source control is achieved at the Aerovox site via the state 21 E program, the interim sediment cap and underlying contaminated sediments can be removed pursuant to the 1998 Record of Decision for the New Bedford Harbor Superfund Site.

Subtidal Capping: Underway during 2020

In very limited areas of the Upper Harbor it was not feasible or cost effective to address the remaining contamination with dredging, and instead EPA intends to install seven multi-layer caps. The locations currently known to require covering/capping are shown in grey on the attached map. EPA intends to issue a future remedial decision document regarding the installation of the cover/caps. These underwater barriers will generally consist of 2 layers; the bottom layer will consist of approximately 24 inches of silty sand which is designed to permanently sequester the PCB contaminated sediment below. The silty sand layer will be covered by a rocky armoring layer approximately 12 inches thick. The armoring layer will serve to protect the silty sand layer below. Periodic bathymetric surveys will be conducted to ensure the integrity of the subaqueous cover/caps.

Intertidal Cleanup: In Progress

Through 2019, EPA funded the removal of about 34,000 cubic yards of sediments from the shoreline (intertidal cleanup), followed by disposal off-site. During the course of 2020, approximately 20,000 cubic yards of sediments from the shoreline area in the northern part of the Upper Harbor will be excavated, followed by disposal off-site. Disturbed saltmarsh areas will be replanted mainly during the Spring of 2021.

The next step after this work is completed is more intertidal clean up. About another 34,000 cubic yards of intertidal cleanup will be necessary in the Upper Harbor. This cleanup will take place in the upcoming years as funding becomes available from the Superfund program.

Top of Page


How did EPA conduct the dredging work?

A hybrid, or full-scale dredging process, removed contaminated sediment from the harbor bottom by a system of dredges, pipelines and processing facilities. Before areas were dredged, any large debris such as tires, mounds of bricks, etc were removed from the harbor bottom to avoid any damage to the equipment. Once the areas were cleared, a highly accurate dredge bucket collected contaminated sediment, and then transfered the resulting mix of water and sediment through an underwater pipeline to EPA's de-sanding facility Exit on Sawyer Street in New Bedford. The coarse sand and shells were filtered from the sediment and silt that contain most of the PCB contamination. The filtered coarse material was temporarily stored and tested at Sawyer Street before it was sent to an off-site, licensed disposal facility. The remaining silt and water was pumped 1.4 miles south to EPA's de-watering facility Exit, where large filter presses squeezed water from the silt. EPA treated the water Exit to strict water quality standards before it was released back into the harbor, while the dewatered sediment was safely transported to a licensed PCB landfill in Michigan.

  • Following the discovery of a shipwreck in 2009 (PDF) (13 pp, 1.7 MB), as well as an anchor of possible historic value in late 2010, archaeological surveys are conducted as necessary and an "on-call" marine archaeologist is available should additional artifacts be uncovered during the cleanup work. Subsequently, 2 more shipwrecks were discovered first in the upper harbor (2016) (PDF) (184 pp, 47 MB) & in the lower harbor (2017) (PDF) (233 pp, 67.5 MB).

During active cleanup work, EPA monitors the air and water quality Exit to ensure that environmental quality is not impacted and that the cleanup continues to be protective for the workers and surrounding communities. Additionally, EPA is working with the adjacent cities and towns to ensure that fishing restrictions and exposure risks continue to be communicated to the public.

Top of Page


Current / Upcoming Work

During 2020 the following construction work is anticipated:

  • Completion of remediation of intertidal shoreline areas "EZ-1" and "WZ-1" in the Upper Harbor
  • Completion of subtidal caps in the Upper Harbor at seven locations
  • Completion of demobilization and decontamination at the former dewatering plant on Hervey Tichon Boulevard in New Bedford.
  • Demobilization of contractor equipment and personnel from the 103 Sawyer Street complex.

Top of Page


How much longer will this cleanup take?

The focus of cleanup in the Upper Harbor shifts towards the shoreline going forward. This shoreline remediation will proceed north to south on both sides of the river, beginning at the eastern shoreline in Acushnet, closest to the Wood Street/Slocum Street Bridge. After shoreline soils/sediments above cleanup levels have been removed for disposal, the excavated areas will be backfilled with clean topsoil and replanted as saltmarsh. Other cleanup work that is needed going forward includes demobilization of cleanup equipment, facilities and personnel; disposal off-site of temporarily stored contaminated sediment currently at the 103 Sawyer Street facility, assessment of the Interim Aerovox Cap, and capping of the Lower Harbor CAD Cell.

Enormous cleanup progress has been made with the proceeds that were secured from the 2013, $366.25 million settlement. The specific timing of remaining cleanup activities will depend on funding levels available to the project year by year.